From: Christie, William
Sent: Monday, July 25, 2005 8:42
AM
To: O'Brien, Edward
Cc: Lynch, Don; Aronson, Samuel;
Ludlam, Thomas W; Pile, Philip H; Brown, Ralph L; Christie,
William
Subject: Re: Proposed schedule for Run-6
Dear
All,
Below please find the STAR input for the discussion
on the preferred start date for the FY06 run.
Greetings,
Bill
Schedule if we
install the FMS Platform during the current (FY05) Summer
Shutdown
---------------------------------------------------------------------------------------
1.) The main driving task for the start of
the FY06 run, from STAR's
perspective, is to get the new platform
installed on the West tunnel
alcove of the STAR Hall, for the Forward
Meson Spectrometer (FMS) detector.
- It is our opinion that
getting the platform installed during the
current shutdown will allow us to install the FMS
detector onto the
platform during the FY06 Summer Shutdown, in preparation
for the FY07 run.
- A corollary to item 1 is that we
don't believe that we can install
both the platform and the FMS detector
during a single (i.e. FY06 )
SUmmer Shutdown
period.
- We need sufficient time after the
FMS platform is installed to get
the STAR detector back into the Wide Angle
Hall (WAH), get it hooked up,
commissionind, and ready for the FY06
Physics run.
2.) A second consideration concerning the
optimum start date is the
completion of the Barrel Electromagnetic
Calorimeter (BEMC) electronics,
prior to the start of the FY06
run.
- Our estimate at this time is that
we'll just get the last of the
BEMC electronics installed by November 1st.
At least a few weeks will
be required to commission and debug this
electronics after it is installed.
Schedule
Components
-----------------------
* FMS Platform pieces fabricated and
delivered to STAR (July 25 to
August 31)
- Work to be done by BNL Central
Shops
- Central
Shops estimate is that FMS platform pieces will be
delivered by end of
August.
* Installation of FMS platform in the STAR Hall (Sept. 1
to October 14)
- Estimated
time to accomplish this, including reinstalling new
RHIC vacuum pump stand, and assorted utilities in /on
platorm area is
1.5 months.
* Move the STAR Detector back into the WAH
and connect all utilities
(Oct. 17 to Oct.
28)
- Endcap
Electromagnetic calorimeter (EEMC) needs a few days
after the platform is installed and before STAR is moved
into the WAH.
* Certify interlock systems, debug and commission sub
systems,
integrated STAR tests (Oct. 28 to Nov
25)
- typically takes the better part of
a week to certify the
interlocks. During this time it is difficult to test
systems.
- 3 wks is about the minimum required
to test, debug, and commission
all of the sub systems individually, and
then as an integrated system.
* Allowing for a slip of a week in
any portion of the plan (as well as
Thanksgiving last week of Nov.) leds to an earliest
start date (with FMS
platform installed) of about December
5th.
Schedule if we DO NOT install the FMS Platform during
the current (FY05)
Summer
Shutdown
-------------------------------------------------------------------------------------------------
1.) If we don't install the FMS during the
FY05 Shutdown, the driving
issue for our preferred start date is the
completion (including
debugging and commissioning) of the BEMC
electronics.
- It is anticipated that a major
portion of the FY06 run will be
polarized protons. To make best use of this
beamtime we need the
complete BEMC and EEMC sub systems operational, as well
as the other
STAR components.
Schedule
Components:
-----------------------
* We could move the STAR detector back into
the WAH during the 1st two
weeks of October (Oct. 3 to Oct.
14)
- We may even be able to move into
the WAH a bit earlier than this
* Certify interlock systems, debug and
commission sub systems,
integrated STAR tests (Oct. 15 to Nov
15)
- typically takes the better part of
a week to certify the
interlocks. During this time it is difficult to test
systems.
- 3 wks is about the minimum required
to test, debug, and commission
all of the sub systems individually, and
then as an integrated system.
- This assumes that we
get started on debugging and commissioning
the BEMC electronics early in this period, and then test
the last
components of BEMC electronics as they come out of the
Lab and get
installed on the
detector.
* If one allows for a slip of a week in some portion of
the schedule,
this leds one to a start date of ~ Nov.
21st.