We have money for 17 weeks of RHIC running. That means 5 weeks of polarized protons. Because of the extra week of Set-Up required for 500GeV running, this makes it much more likely that only 200GeV running will be considered. There are attempts to get an extra week of pp running time; i.e. 6 weeks of pp. If the extra week of pp running is possible, there may be time to do a 2 week 200GeV run followed by a 1 week 500GeV run (with a week of development in between).
Here is a brief summary of the schedule as
discussed in the meeting, making the assumption that there will be 5 weeks of pp
running, It will certainly be superseded by discussions Tuesday afternoon,
but it provides milestones to look at.
Jan 9 APEX 5AM - 5PM
(Vacuum work gets done in Booster)
Jan 15 APEX 8PM - 8AM Jan 16
Jan 16 Maintenance 6AM - 6PM
Jan 17 AGS Cold Snake is cold
(Polarized Proton development behind stores)
Jan 19 (Au-31+ behind stores,
coordinated with pp)
Jan 23 APEX 5AM - 5PM
Jan 31 d-Au running complete
Feb 1 Switch Q7 polarity / ZDCs
Feb 2 Set-up for pp at ? GeV
Feb 16 pp running
Mar 1-7 pp ends.
(Low Energy Au-Au running?)
Projects for a long shutdown: