|
C-AD Accelerator R&D Division
Superconducting RF Group
56 MHz SRF Storage Cavity for RHIC, 2nd External Review, March 8-9, 2011
Review Agenda
Review Committee Members
• John Weisend, FRIB, Michigan State University, Chair
• Charlie Reece, SRF Institute, Jefferson Laboratory
• Jim Rose, NSLS-II, Brookhaven National Laboratory
• Jon Sandberg, C-AD, Brookhaven National Laboratory
• Joe Tuozzolo, C-AD, Brookhaven National Laboratory
Charge to the committee
A review was held January 8-9, 2009 of the RHIC 56 MHz
Superconducting Storage Cavity. That review addressed issues of physics
design and engineering design in progress. Since that time the C-AD team has
addressed the open issues identified by the review panel, implemented
recommended changes, continued R&D and began fabrication phase of the
project. Among actions taken in response to the committee recommendations
are: i) a detailed plan of acceptance and commissioning was added to the
overall schedule; ii) off normal events on the cavity (quenches, vacuum
breaks, etc.) will be incorporated into the machine protection system, which
will dump the beams when necessary; iii) the tuner plate region was
re-designed and cooling was added to the tuner plate; iv) LHe cooling was
added to HOM dampers. We ask the committee to review current state of the
project and respond to the following questions:
- Are the cost and schedule reasonable for this stage of
the project
- Review the testing and performance goals. Are proposed
tests and procedures sufficient to reach those goals? Is
tooling for the cavity processing and string assembly
adequate? Does schedule provide enough time for testing?
- Evaluate the cavity and vacuum vessel design,
fabrication progress and schedule.
- Evaluate the cryomodule design (tuner, vacuum vessel,
shielding, support system).
- Review and comment on the designs of HOM and fundamental
power dampers, FPC.
- Evaluate the use of an IR detector as a method to detect
quench of HOM dampers.
- Review RF and vacuum sub-systems. Comment on soundness
of their design and implementation.
- Are there open technical risks? If so, what additional
steps are necessary to adequately answer them?
Tuesday, March 8th
8:30 Executive Session: Charge to
Committee/Continental Breakfast - S. Belomestnykh
9:00 Welcome - I. Ben-Zvi
9:10
Introduction to the 56 MHz Project Review - S. Belomestnykh
9:30
Overview of RHIC Layout, 56 MHz Cost and Schedule - G. McIntyre
10:15 Coffee Break
10:30
Testing and
Performance Goals - Q. Wu
11:00
Cavity & Helium Vessel Design Overview, Fabrication Progress, and Schedule
- C. Pai and G. McIntyre
11:45
Tuner Design Overview, and Schedule - C. Pai
12:15 Lunch
1:15
Vacuum Vessel, Shielding, Support System: Design Overview, and Schedule
- C. Pai
1:45
HOM & Fundamental Dampers, FPC: Design, Fabrication, and Schedule - S.
Bellavia
2:30
Tooling for Cavity Processing and String Assembly – C. Pai
3:00 Coffee Break
3:15
IR Detector – B. Sheehy
3:45
Cryogenic System , Cryogenic Instrumentation - R. Than
4:30 Executive Session
5:00 Questions, Homework Assignments from the
Committee
5:15 Adjourn Day 1
6:30 Dinner
Wednesday, March 9th
8:30 Executive Session/Continental Breakfast
9:00
LLRF System - K. Smith
9:15
Vacuum
System and Instrumentation - M. Mapes
9:30 Response to Questions/Homework:
Off Normal events - S. Belomestnykh
Schedule and Facilities - G. McIntyre
10:00 Coffee Break
10:15 Executive Session/Report Writing
11:30
Closeout
12:00 Adjourn
Committee Report
56 MHz Project Review Final Report
|