Time Meetings resume 16 September 2008 at 13:30 in the Snyder Auditorium.
RHIC
There is not yet a firm schedule for the RHIC Run 09.
Cooldown starts Jan 1, with physics running starting Feb 1 2009.
If we get a budget, then we run 21 weeks or so. Run at 500 and 200 GeV, predominantly longitudinally polarized protons.
If we don’t get a budget, then we run at 500 GeV only. Under a continuing resolution, we will do 3 weeks of physics at 500 GeV of longitudinally polarized protons (plus a little bit of transverse to characterize the local polarimeters).
First plane of stochastic cooling is on schedule for a Feb 1 start-up.
Spin flipper will go in one of the rings, to be used for testing.
9 MHz is in and under test.
Polarimeter is getting a new vacuum chamber, with independent vertical and horizontal target mechanisms.
NSRL
NSRL Run 08C begins 29 September 2008 running through 21 November 2008.
Paul Sampson's Start Up Schedule can be found here.
Scheduling Physicist: Mike Sivertz | Last updated: |
Email: sivertz@bnl.gov | |
Office Phone: 631-344-6102 | |
Digital Pager: 7528 or 4300 | |
Home Phone: 631-878-9020 and leave message. |